03-083-11419-00-00 | Operator | 01-01-1900 | 32 |
03-083-11419-00-00 | Original Permit | 01-01-1900 | 46487 |
03-083-11419-00-00 | Pressure Tests Received | 01-01-1900 | |
03-083-11419-00-00 | Date Permit Issued | 03-20-2013 | Form: 2 | original |
03-083-11419-00-00 | Date Commenced | 04-11-2013 | Form: 3 | Date commenced. |
03-083-11419-00-00 | Date Well Spudded | 04-11-2013 | TRK |
03-083-11419-00-00 | Completion Type | 07-01-2013 | Controlled Production |
03-083-11419-00-00 | Date Completed | 07-01-2013 | TRK |
03-083-11419-00-00 | Well Status | 07-01-2013 | PR |
03-083-11419-00-00 | Date Completed | 07-24-2013 | Form: 3 | Initial completion in Desmoinesian / U. Carpenter. |
03-083-11419-00-00 | Commingle Request Received | 08-02-2013 | |
03-083-11419-00-00 | Date Completion Form Received at AOGC | 08-02-2013 | TRK |
03-083-11419-00-00 | Form 4 (CoC) Received | 08-02-2013 | |
03-083-11419-00-00 | Log Received | 08-02-2013 | |
03-083-11419-00-00 | Commingle Request Approved | 08-21-2013 | |
03-083-11419-00-00 | Initial Date Allowed to Produce | 08-21-2013 | |
03-083-11419-00-00 | Other | 08-21-2013 | Date Certificate of Compliance (CoC) issued; Commingle Permit - Auth/Com Desmoinesian & U. Carpenter. |
03-083-11419-00-00 | Tracker Finish Date | 08-21-2013 | |
03-083-11419-00-00 | Date Completion Form Received at AOGC | 08-23-2013 | Form: 3 | Rcv'd Amended Form 3 to correct Pool name. |
03-083-11419-00-00 | Other | 11-17-2015 | Form 33 apprv'd - Temporarily Abandoned. Status Date changed from 8/21/13. |
03-083-11419-00-00 | Date Completion Form Received at AOGC | 08-04-2016 | Form: 3 | Rcv'd Form 3 to return well from TA status and to receive CoC. |
03-083-11419-00-00 | Other | 08-04-2016 | Date Certificate of Compliance (CoC) issued to return from TA status. |
03-083-11419-00-00 | First Production | 08-08-2016 | |
03-083-11419-00-00 | Other | 08-08-2016 | Date of Commencement of Production - NoCoP rcv'd 8/11/16. |
03-083-11419-00-00 | Wellbore Status | 08-08-2016 | Active |
03-083-11419-00-00 | Date Workover Commenced | 01-23-2017 | Form: 3 | Date workover commenced. |
03-083-11419-00-00 | Date Completed | 02-02-2017 | TRK |
03-083-11419-00-00 | Date Workover Completed | 02-02-2017 | Form: 3 | Workover - Ran tubing. |
03-083-11419-00-00 | Date Completion Form Received at AOGC | 02-09-2017 | TRK |
03-083-11419-00-00 | Tracker Finish Date | 02-22-2017 | |
03-083-11419-00-00 | Deviation Type | 05-15-2024 | Vertical |
03-083-11419-00-00 | Operator | 05-15-2024 | 32 |
03-083-11419-00-00 | Well Name | 05-15-2024 | Schmalz |
03-083-11419-00-00 | Well Number | 05-15-2024 | 2-7 |
03-083-11419-00-00 | Well Type | 05-15-2024 | GAS |
03-083-11419-00-00 | Wellbore Type | 05-15-2024 | Natural Gas - Dry |